Project Background & Timeline

    ODEQ Consent Order Received — May 2020

    Federal Funding Through ARPA Secured — December 2022

    Design Phase Completed — July 2024

    Broke Ground — February 2025

    Commissioning Expected — Fall 2026

    Full Project Completion — Spring 2027


Frequently Asked Questions

    How much will the wastewater treatment facility cost?


The new facility will cost $59 million to build, but federal funding through the American Rescue Plan Act (ARPA) will cover $44 million of the cost—saving residents millions of dollars.

    How does building a new wastewater treatment facility benefit Glenpool?


The new facility is designed to replace the current lagoon-style system and will effectively double the capacity, enabling the City to modernize its utility infrastructure and provide improved service to residents.