UPDATED 8/27 This is the current schedule of the start and completion dates for each project location as of July 16th. These dates will likely change along the way so the schedule will be revised each Wednesday to reflect what was completed the previous week. The schedule will be updated each Wednesday to reflect completed projects and any new dates for the remaining projects if everything has shifted due to weather or other delays.
A map of the location can be viewed by clicking on the project number.
2019 STREET REPAIR PROJECT SCHEDULE
Project Number: | Estimated Construction Dates: | Completed |
#16 | July 17 - 24 | Completed |
#1, 2 | July 17 - 26 | Completed |
# 3, 6, 7, 18 | July 26 - August 6 | Completed |
# 8, 19, 20 | August 5 - 16 | Completed |
# 4, 5 | August 15 - 19 | Completed |
# 10 & # 9 | August 19 - 21 | Completed |
# 17 | August 22 - 26 | Completed |
# 11, 12, 13, 14 | August 26 - 30 |
|